- Dynamic Test Stand modifications
- First stage main parachute cluster drop testing
- Upper stage manufacturing facilities and tooling
- Chemical steam generator testing
- Test Stand A-3 Construction Progress
Sunday, July 12, 2009
NASA's Ares Quarterly Progress Report
This Ares Quarterly Progress Report, originally released to the public June 1, 2009, includes progress updates on: